WUA Bereke-S

Map of the WUA Bereke-S Manas district, Talas region

АВП Токтомуш

Information

Total cost

20 943 488 som

Contractor

Talassuukurulush Consortium

Serviced area

1161 hectares

Execution plan

20 943 488 som

Water users

380 people

Actual execution

20 943 488 som

Сроки

03.01.18 – 12.10.18

Status

completed - 100%

In 2020, the facility was put into operation by the WUA “Bereke-S” on the basis of the act of the State Acceptance Commission dated December 10, 2018, approved by the territorial department of the State Inspectorate for Environmental and Technical Safety in the Talas region.

Peasant farms- 450

Agronomy data
Crops Productivity, kg/ha Yield increase
Without the project/basic Actual execution for 2020  +/- in kg in %
Winter wheat 2 000 2300 300 15%
Spring wheat 2 500 2070 -430 -17%
Barley 1500 2040 540 36%
Corn 3 400 6580 3 180 94%
Perennial herbs 6 800 6924 124 2%
Beans 1 300 1400 100 8%
Sugar beet 20 000 33000 13 000 65%
Potato 21 000 20150 -850 -4%
Vegetables 22500 23010 510 2%
Gardens 4000 3710 -290 -7%
Purchase of agricultural machinery / agricultural crops

Tractor (1)

1,545,600 units/som

Tractor trailer

267,000 units/som

Plow

98,000 units/som

Field Sprayer

100,000 units/som

Population​
  • Target ayil okmotu

    Uch-Korgon

  • Number of villages in RA (rural area)

    12

  • Population of the NSC (National Statistical Committee)

    20763

  • Neighboringayil okmotu

    Pokrovka

  • Households

    3 751

  • AO/FGP population

    19 115

  • Women of reproductive age

    3 337

  • Teenage girls

    527

  • Children aged 0-5 years

    3 082

We ask you to timely fulfill the obligations for the return by associations (associations) of water users and unions of water user associations of state borrowed funds recredited by the Government of the Kyrgyz Republic under the project “Improvement of Agricultural Productivity and Nutrition”